Posted on: April 10, 2020

[ARCHIVED] Active Elk River Progress Report - March 2020

East Rink Pour PicOperational changes in response to the COVID-19 pandemic didn’t slow RJM Construction crews and contractors from accomplishing major milestones on the multipurpose facility during the month of March, including concrete pours on both the west and east arenas! Check out this time-lapse video of the east rink surface concrete pour – an all-day process utilizing 10 concrete trucks and flowing concrete at a rate of 75-80 yards-per-hour.

Click here to check out the full Active Elk River Progress Report for the month of March, or you can visit ActiveElkRiver.com.