December left Active Elk River crews faced with sub-zero temps, snowstorms, holiday scheduling conflicts and more – but despite all that, things at the multipurpose facility and Lion John Weicht Park are on schedule and progressing nicely!
At the multipurpose facility, stadia seating was completed in both the east and west arena, joist and decking was finished which made way for roofing crews to mobilize on site.
To the south at Lion John Weicht Park, blockwork on the concession/restroom building was completed along with the bleachers for Field #1 and #2.
Check out the full December 2019 progress report here. Also, sign up for Notify Me to ensure you never miss an update!