November was full of action for Active Elk River construction crews. At the multipurpose facility site, cranes placed 140 interior structural walls, steel roof trusses were placed, and stadia seating installation began in the west arena. Across the street at Lion John Weicht Park, outfield and backstop fencing was installed, blockwork began on the concessions/restroom building, and the parking lot had fresh curb, gutter, and pavement put in.