Construction season is here and year 2 of the #169redefine project is set to start next week. Here is what you can expect (weather depending):
- 193rd Ave is set to close March 28 at 7:00 p.m.
- School St. is set to close April 2 at 7:00 p.m.
- Signals at both above intersections will be removed once streets are closed. Right-turn ins/outs will be available and maintained on the east side at both 193rd Ave and School St. until mid-April.
- Southbound and northbound traffic will flow through the intersections uninterrupted except for needed lane closures during bypass construction along the west side of 193rd Ave and School St.
- Once bypasses are complete, the next stage is to move to a head-to-head configuration along southbound 169.
- More details to come as we get closer to the end of bypass construction.
Have more questions or want to see the full picture of what construction will look like? Stop by City Hall tonight, Tuesday, March 21 from 4:00 – 6:00 p.m. for our 169 Redefine Open House.
Can't make tonight? Click here to view the 2023 169 Redefine Open House Fact Sheet.