2019 Street Improvement Projects

*Updated June 14, 2019*Street Reconstruction

2019 construction season is upon us and Public Works crews will be busy this summer with several mill and overlay and street reclamation projects throughout Elk River. Mill and overlay is a street maintenance technique that requires removal of the top (1.25 inch) of a road surface and the addition of a new (1.5 inch) layer of bituminous pavement. Reclamation is a full reconstruction of the roadway, where the entirety of the existing pavement is removed down to the gravel base of the street and replaced with new pavement. For a map of 2019 projects, click here.

Mill and Overlay Projects

226th Ave. NW to Jarvis St. NW

Paving of both areas has been completed.  Crews will soon restore disturbed areas with topsoil and seeding.

214th, 215th, 217th, 225th Ave. NW to Fresno St. NW

Work has been completed on 214th, 217th,  225th, and Fresno St. NW. 

All Milling and concrete work on 215th has been completed.  Paving is planned for the week of June 17.

Fresno St. NW to Concord St. NW

Work has been completed on Fresno St. NW and Concord St. NW.

York, Watson, Vernon St. NW to 212th Ave. NW

The southern piece of York and Watson St. have been completed.

Paving of the non-wear course is tentatively planned to be finished today or next Monday. The northern piece of York, Vernon St. NW and 212th Ave. NW are planned to be paved with wear course by next week.

There are areas where the poor soil quality has reflected to the newly placed road base.  Please be aware crews will be fixing this issue by replacing the clay with a quality soil capable of stabilizing the roadway before ultimately completing the construction.

Upland, Vernon, Rush St. NW to 194th, 195th Ave. NW

Work has been completed in this area.

*Please exercise extreme caution in this area and proceed slowly*

193rd Ave. NW, Dodge, Auburn, Zane St. NW to Carson Circle NW

Paving in this area is expected to be complete by the end of today.  Crews will then be filling disturbed areas with topsoil and seeding shortly after.

*Please exercise extreme caution in this are and proceed slowly*

Reclamation Projects

Proctor Ave. NW

Area has been reclaimed and all concrete work is complete.  Shaping of the base will begin early next week.

Because of the heavy traffic on this road, please seek alternate routes during construction in order to help speed up the construction process.

Ranch Rd. NW

Work has been completed on Ranch Rd. NW.

Baldwin St. NW

Area has been reclaimed.  Required subgrade work will then begin where necessary.  Paving is likely to occur during the week of June 17.

215th Ave. NW

Area has been reclaimed and the concrete sections have been poured.  Subgrade and base work has begun and will be complete early next week.  Paving is likely to occur during the week of June 17.

York St. NW

Reclamation has been completed.  Paving of the non-wear course has been completed, but requires some additional work because of inadequate soils beneath the surface.  After these soils are replaced, the areas will be patched with the non-wear mix prior to paving the final lift of asphalt.

211th Ave. NW

Reclamation has been completed.  Paving of the non-wear course has been completed, with the final lift of asphalt expected next week.