2021 Street Improvement Projects

*Updated September 13, 2021*Street Reconstruction

2021 construction season is upon us and crews will be busy this summer with several mill and overlay and street reclamation projects throughout Elk River. Check back for updates as work progresses. The time frames listed may change due to weather and/or other delays.   

Mill and overlay is a street maintenance technique that requires removal of the top (1.25 inch) of a road surface and the addition of a new (1.5 inch) layer of bituminous pavement. 

Reclamation is a full reconstruction of the roadway, where the entirety of the existing pavement is removed down to the gravel base of the street and replaced with new pavement.

Mill and Overlay Projects

ER_Map_Construction_April 21 Opens in new window201st Ave, 197th Ln, Naples St, 199th Ave, Pascal St, 200th Ave, Rawlins St, Troy St 
Crews have completed work this area. Restoration will continue until turf is re-established in affected areas.

Dodge Ave, Dodge St, Evans St, 190th Ln, 190 1/2 Ln, Evans Cir
Crews have completed work in this area. Ongoing restoration of this area will continue in the coming weeks until turf re-establishment is achieved.

Zebulon St, 190th Ave, 189th Ln, Waco St, Xerxes St
Crews have completed work in this area. Ongoing restoration in this area will continue in the coming weeks until turf re-establishment is achieved.

Trott Brook Pkwy
Crews have completed work in this area. Ongoing restoration in this area will continue in the coming weeks until turf re-establishment is achieved.

Industrial Cir, 179th Ave, Zane St

Work on Industrial Cir has been completed. 179th and Zane St will begin next week and will take 2-3 weeks.

Reclamation Projects

190 1/2 Ave, Xerxes St

Paving is complete and restoration will follow until turf is re-established.

Jackson Ave

This area is now complete. Crews will continue performing restoration in the coming weeks in order to establish vegetation in disturbed areas.

Remove & Replace Pavement Projects

Twin Lakes Road (Northbound and Southbound)

Work is ongoing near the railroad tracks and on 171st Ave. This phase will be completed toward the end of September. Final completion of Twin Lakes Road is anticipated for mid-October.

Thank you for your patience during all construction-related work.